Gov Uba Sani Has Spent N8. 2 bn On Kabala-Costain Road—KADRA MD

Governor Uba Sani has disbursed a total of N8.2 billion for both the payment of inherited debt and mobilizing contractors to complete the abandoned Kabala-Costain road project.

Giving an update on the project, the Managing Director of Kaduna State Roads Agency(KADRA), Dr Abdullahi Baba Ahmed said that the project was abandoned by the previous administration due to major design flaws and funding challenges.

Dr Ahmed who spoke with newsmen when he visited the project site with his team, explained that Governor Uba Sani cleared the inherited debt of N2.2 billion owed the contractor and mobilized CCECC to site with N6 billion.

The Managing Director further explained that a total of N8.2 billion has been expended on the project, promising that the road will be ready next year.

He further explained that Governor Uba Sani had inherited the Kabala-Costain road project at only 35 percent completion, contrary to the false claims of the previous administration.

Speaking at the project site, the Chief Consultant of the road dualisation project, Engr Shakirudeen Adesina Akinloye recalled that the contract was awarded in 2020 but the project was stalled in 2022, due to major design flaws and payment issues, forcing the contractor, CCECC, to suspend work.

The Chief Consultant further explained that the Uba Sani administration did not only revive the project, but also cleared a ₦2.2 billion debt owed by the previous government.

“The project stopped at 35 percent before the current administration took over. When we resumed, we discovered the initial design was unsafe, it had a sharp curve immediately after the bridge, which could cause accidents. We redesigned it to ensure smooth traffic flow and safety,” he said.

According to Engr Akintoye, the intervention of Governor Uba Sani prevented further deterioration of the site.

“The initial design had engineering flaws. The redesign now includes a gentle curve and a second bridge to address flooding and safety concerns. Safety comes first in engineering,” he added.

The Chief Consultant disclosed that the new design also has an additional bridge similar to first one, to handle waterlogging challenges, as soil tests showed the subsoil depth in the area is about nine meters.

“Rather than spending more to stabilize the soil, the present government approved a second bridge, which is both faster and cheaper,” he clarified.

Explaining further, the Managing Director of KADRA, corroborated the consultant’s statement, stressing that the project was abandoned midway by the last administration.

Dr Baba Ahmed also reiterated that the Governor Uba Sani administration inherited the project at just 35 percent completion.

He said only one bridge and about 600 meters of road, out of the total 2.7 kilometres, were completed before the project was abandoned, representing roughly 22 percent of the total work scope.

“This administration came on board in 2023 and revived the project. It paid an outstanding ₦2.2 billion owed to the contractor and released an additional 50 percent advance payment for outstanding works,” Dr. Ahmed said.

The MD of KADRA dismissed reports that the previous government achieved up to 70 percent completion, describing the claim as “pure misinformation.”

“It’s simple arithmetic, not mathematics. Six hundred meters out of 2.7 kilometres is 22 percent. This administration is constructing the remaining 2.1 kilometres and a second bridge,” he clarified.

Dr. Baba Ahmed also explained that new engineering solutions became necessary after investigations revealed that the initial alignment narrowed the water channel, causing flooding during the rainy season.

“We had two options, either spend heavily on soil stabilization or extend the bridge. We chose the latter because it’s safer and cost-effective,” he said.

The MD commended Governor Uba Sani for taking the bull by the horns to complete the project despite the financial burden that his administration inherited.

“This administration is committed to delivering quality infrastructure. It didn’t abandon the contractor’s debt, it paid it off and pushed for speedy completion,” the KADRA boss added.

Project Manager for CCECC Kaduna Office, Mr. Henry Zhang, also confirmed that the project stalled due to unpaid certificates and adverse ground conditions, adding that the company had since received advance payment from the present government and that they have resumed full-scale operations.

“With the leadership of Governor Uba Sani, the project has been revived and is progressing smoothly. We are determined to deliver a high-quality road that will improve traffic flow, connect communities, and support Kaduna’s economic growth,” Zhang said.

The Kabala–Costain dualisation project, spanning 2.7 kilometres, links Aliyu Makama Road and Costain Junction in Kaduna North.

When completed, it is expected to ease traffic congestion, prevent flooding, and enhance economic connectivity between Kaduna North and Kaduna South.

Recent Post

Birnin Gwari: Kaduna Is Grateful To Mr President—Uba Sani President Bola Ahmed Tinubu has flagged off the 122-kilometre Kaduna-Birnin Gwari road project on Tuesday, in fulfilment of his campaign promise as the then presidential candidate of the All Progressives Congress(APC) over three years ago. Represented by Governor Uba Sani, he recalled that on the 22nd December , 2022, Tinubu came to Kaduna during the campaign and visited Birnin Gwari in defiance to security advice. He said that at that time, Birnin Gwari was the epicentre of banditry, kidnapping and insurgency, but Tinubu had argued that ‘’as someone who was aspiring to be president of Nigeria, he must visit Birnin Gwari.’’ According to the Governor, the then ‘’GOC of One Mechnised Division, the late General Lagbaja, gave us 21 Armoured Vehicles with military personnel, to Birnin Gwari.’’ ‘’We left Kaduna at about 4pm, we arrived Birnin Gwari after four and half hours because the road was bad and we got there around 8:30pm. At the Emir’s palace, His Royal Highness graciously honoured the presidential candidate with a traditional title. Governor Uba Sani disclosed that Asiwaju had ‘’promised that he will reconstruct the road from Mando in Kaduna, to Birnin Gwari. He also promised that he will do everything to ensure that security and normalcy return to Birnin Gwari.’’ ‘’Today, President Bola Ahmed Tinubu has fulfilled all the two promises he made to the people of Birnin Gwari. I’m happy that we are here for the ground breaking of this very important road,’’ he added. The Governor further said that the road is very critical because it connects the whole North West to the South west, cutting across five states up to Lagos, adding that N178 billion has been approved for the project. Describing the Minister of Works, Senator David Umahi as a go-getter and a detribalised Nigerian, he disclosed that they worked together to ensure that the money was approved for the project. Governor Uba Sani expressed gratitude to the president that people can now travel from Kaduna to Birnin Gwari and within the town, without a police escort. He disclosed that Birnin Gwari did not benefit from even one kilometre of road project in the last 20 years until the present administration came into office about three years ago. ‘’Today, Kaduna State Government is constructing 36 kilometres of asphaltic roads, cutting across 72 farming communities in Birnin Gwari local government area,’’ he added. The Governor pointed out that the flag off of the Kaduna-Birnin Gwari road and the various road projects within Birnin Gwari local government, represent the dividends of peace. According to him, President Tinubu has a special love for Kaduna State that is why, ‘’on the 8th of July, he approved $865 million for the construction of the Light Rail project in Kaduna metropolis.’’ ‘’The Western bye-pass project is ongoing, from Abuja junction down to Kawo motor park. This project is being undertaken by the Federal Ministry of Works under the able leadership of the President. ‘’We are also talking about resuming the construction of the Eastern bye-pass, which is very critical to our people. I have no doubt that project will be resumed, according my conversation with the Minister, in a few month’s time. ‘’We are grateful to Mr President. We will continue to support him and I have no doubt in my mind that the 2027 election has been concluded. We are giving Mr President, at least 95% of our votes,’’ he added. Speaking earlier, the Minister of Works, Senator David Umahi, had described President Tinubu as ‘’a promise keeper, a man that rewards loyalty. He is a man that is fair to every section of the country.’’ The Minister said that he is not surprised at Governor Uba Sani’s developmental strides in Kaduna State because he is ‘’a man who fought along side with our president during the days of NADECO, who was unjustly put in cell.’’ ‘’You understand the meaning of democracy . You understand the meaning of welfare to the people. You have united the entire Kaduna people. You are delivering a lot of infrastructure for the people,’’ he added. Senator Umahi recalled that when he last visited Kaduna State on a site inspection tour, ‘’I said that you are magical like your father, the president. I commended you very highly and I thanked you for uniting the entire Kaduna people.’’